At Pewsham, our bricklayers have finished restoring the dry-dock walls, our architect has submitted the latest drawings and amendments and Marsha Miles fundraisers continue to locate funds for this project. We will soon be at the stage where we can start bringing materials on site. Bob, our chippy, has indicated that oak seasons very quickly and, once this has happened, the wood is extremely hard to work with. The plan therefore will be to have green oak delivered so we can produce A-frames one at a time and, once all eight are constructed, we can start the erection phase.

Below are images of the dry-dock before and after the work

DF161 07 Dry Dock Before  DF161 07 Drydock 2